Rain is expected on the Hurley Thurs/Friday and the FLNRO avy technician analysis is if the Green Mtn avy path’s don’t come down then,  the risk is about the same as driving on the Duffy  i.e. lower. They feel that crews doing road work can travel in and out at that point more safely. The plan is to replace the steel bridge deck next Tuesday to Friday.

On Saturday there will be another assessment of snow depths on Hurley steel bridge to Pembie side and then determination will be made if clearing will start.  Next update likely Sunday and frequently as possible after that.

Thanks to FLNRO for the update and the photo.